Claus Ibsen commented on CAMEL-11632:
-------------------------------------

You are welcome to work on a contribution

> QuartzScheduledPollConsumerScheduler causes trigger misfires on each 
> application start
> --------------------------------------------------------------------------------------
>
>                 Key: CAMEL-11632
>                 URL: https://issues.apache.org/jira/browse/CAMEL-11632
>             Project: Camel
>          Issue Type: Bug
>          Components: camel-quartz2
>    Affects Versions: 2.19.0
>         Environment: *strong text*
>            Reporter: Viktor Khoroshko
>
> Recently I noticed that on application start Quartz founds and triggers 
> misfired triggers:
> {code:java}
> INFO o.s.s.q.LocalDataSourceJobStore - Handling 1 trigger(s) that missed 
> their scheduled fire-time.
> {code}
> That wasn't not the realistic case in my scenario - since I could see in a 
> database that NEXT_FIRE_TIME is much ahead of the current time.
> After digging a little I found the issue in the 
> *QuartzScheduledPollConsumerScheduler*:
> {code:java}
>  // Ensure the cron schedule is updated
> CronTrigger newTrigger = 
> existingTrigger.getTriggerBuilder().withSchedule(CronScheduleBuilder.cronSchedule(getCron()).inTimeZone(getTimeZone())).build();
> quartzScheduler.rescheduleJob(triggerKey, newTrigger);
> {code}
> There 2 issues here:
> 1. Job is rescheduled even if nothing has been changed (i.e. cron expression, 
> cron timezone)
> 2.  *existingTrigger.getTriggerBuilder()* returns trigger builder with 
> START_TIME of existing trigger which, surely, is the past. This is causing 
> the described bug - NEXT_FIRE_TIME is calculated based on the old START_TIME 
> and is in the past also. So rescheduled trigger becomes misfired trigger 
> immediately.
> Proposal:
> 1. Do not reschedule job if nothing has been changed.
> 2. If job needs to be rescheduled - make sure to set START_TIME to a current 
> date.



--