https://issues.apache.org/jira/browse/FINERACT-1638?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
]
Dhaval Maniyar updated FINERACT-1638:
-------------------------------------
Fix Version/s: 1.8.0
(was: 1.7.0)
> Overdraft is extended or partially repaid, the interest is not being
> calculated correctly as it is not including previous days interest when
> calculating new interest posting
> -----------------------------------------------------------------------------------------------------------------------------------------------------------------------------
>
> Key: FINERACT-1638
> URL: https://issues.apache.org/jira/browse/FINERACT-1638
> Project: Apache Fineract
> Issue Type: Bug
> Reporter: Vikranth Ramasami
> Assignee: Dhaval Maniyar
> Priority: Major
> Fix For: 1.8.0
>
> Attachments: 1638.JPG
>
>
> !1638.JPG!
>
> * We are expecting the interest applied on 8{^}th{^} June to be 12.78 i.e.
> 1% of 1277.95 (i.e the account balance including previous days
> interest).{+}{{+}}{+}{{+}}
> * Instead the interest is being posted as 12.57 which is 1% of 1257.45
> (which is the sum of only the withdrawal and withdrawal entries).
> The same issue will happen if you say do a withdrawal today and then do a
> partial deposit or another withdrawal the interest posted tomorrow will be
> incorrect
--
This message was sent by Atlassian Jira
(v8.20.10#820010)