https://issues.apache.org/jira/browse/FINERACT-1403?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Aleksandar Vidakovic updated FINERACT-1403:
-------------------------------------------
    Fix Version/s: 1.10.0
                       (was: 1.9.0)

> Advance repayment issue after loan rescheduling
> -----------------------------------------------
>
>                 Key: FINERACT-1403
>                 URL: https://issues.apache.org/jira/browse/FINERACT-1403
>             Project: Apache Fineract
>          Issue Type: Bug
>          Components: Loan
>    Affects Versions: 1.5.0
>            Reporter: Bharath Gowda
>            Assignee: Avik Ganguly
>            Priority: Major
>             Fix For: 1.10.0
>
>         Attachments: after advance repayment.png, before advance 
> repayment.png, product configuration.png
>
>
> The loan repayment schedule is calculating the wrong principal when advance 
> payment is done after the loan reschedule is done.
>  
> To reproduce,
> 1. Create a loan product as per the shared screenshot
> 2. Create a loan account and reschedule any installment and make the payment 
> for the rescheduled date
> 3. Make an advance payment for an installment (for any installment after the 
> rescheduled installment)
> Issue 
> when advance payment is done, the system is changing the principal amount, 
> and in turn, the installment is still not completely paid
> because of this, the loan is considered overdue even if the payment is done 
> on/before time.
>  
> Please find the example screenshot attached of the issue loan with complete 
> explanation and expected result
> please do let me know if you need any more clarification



--