https://issues.apache.org/jira/browse/FINERACT-2279?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Adam Saghy updated FINERACT-2279:
---------------------------------
    Fix Version/s: 1.12.0

> Contract Termination Feature
> ----------------------------
>
>                 Key: FINERACT-2279
>                 URL: https://issues.apache.org/jira/browse/FINERACT-2279
>             Project: Apache Fineract
>          Issue Type: New Feature
>            Reporter: Bharath Gowda
>            Priority: Major
>             Fix For: 1.12.0
>
>
> h3. Background and Details
> A Loan is considered ‘In Default’ when they fail to repay their loan as 
> scheduled by the terms outlined in their contractual agreement, those types 
> of loans are eligible and would under go Contract Termination and Fineract 
> should have a capability to do Contract Termination to Support this Scenario.
> h3. Requirement Details
>  # User with permission should be able to do Contract Termination on a active 
> loan through API
>  # Contract Termination can be done only as of Current date, no backdated 
> termination required
>  # All Installments will be accelerated and become due as of Contract 
> Terminated Date
>  ## Interest till the Contract Terminated Date and the Principal outstanding 
> balance will be the due amount
>  # Maturity date will be updated as the Contract Terminated Date
>  # Delinquency bucketing will continue as per the new accelerated schedule
>  # Charge-off is allowed on the Terminated loan accounts
>  # Charge-backs is allowed on Terminated loan accounts
>  # N+1 Installment will not have any Impact from Contract Termination.
>  # Accrual and Accrual Activity will stop after the termination.
>  ## I believe this happens automatically as we the schedule is accelerated
>  # Account Changed event to be triggered during the Contract Termination 
> activity
>  # No Accounting entry Activity for Contract Termination
>  # If contract Termination is done after the maturity date
>  ## Existing Installments and maturity date remains as is
>  ## Interest calculation will be done only till maturity date (not till 
> contract termination date)
>  # Backdated payments and Reversals to be allowed after contract termination
>  ## Contract termination will be reversed-replayed and adjusted accordingly
>  # Contract termination can be undone/reversed
>  ## Schedule will be recalculated and reapplied accordingly
> Example UCs are here
> https://docs.google.com/spreadsheets/d/1vFvry9rVEIvHuHvXeQ3zhEIevtLsGWAGUmRxI4cIjpE/edit?usp=sharing



--