https://issues.apache.org/jira/browse/FLINK-17726?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=17329039#comment-17329039
 ] 

Flink Jira Bot commented on FLINK-17726:
----------------------------------------

This critical issue is unassigned and itself and all of its Sub-Tasks have not 
been updated for 7 days. So, it has been labeled "stale-critical". If this 
ticket is indeed critical, please either assign yourself or give an update. 
Afterwards, please remove the label. In 7 days the issue will be deprioritized.

> Scheduler should take care of tasks directly canceled by TaskManager
> --------------------------------------------------------------------
>
>                 Key: FLINK-17726
>                 URL: https://issues.apache.org/jira/browse/FLINK-17726
>             Project: Flink
>          Issue Type: Bug
>          Components: Runtime / Coordination, Runtime / Task
>    Affects Versions: 1.11.0, 1.12.0
>            Reporter: Zhu Zhu
>            Priority: Critical
>              Labels: stale-critical
>
> JobManager will not trigger failure handling when receiving CANCELED task 
> update. 
> This is because CANCELED tasks are usually caused by another FAILED task. 
> These CANCELED tasks will be restarted by the failover process triggered  
> FAILED task.
> However, if a task is directly CANCELED by TaskManager due to its own runtime 
> issue, the task will not be recovered by JM and thus the job would hang.
> This is a potential issue and we should avoid it.
> A possible solution is to let JobManager treat tasks transitioning to 
> CANCELED from all states except from CANCELING as failed tasks. 



--
This message was sent by Atlassian Jira
(v8.3.4#803005)

Reply via email to