Owen Nichols created GEODE-8230:
-----------------------------------
Summary: cut pipeline time from 10hrs to 5hrs by running
benchmarks in parallel with other tests
Key: GEODE-8230
URL: https://issues.apache.org/jira/browse/GEODE-8230
Project: Geode
Issue Type: Improvement
Components: ci
Reporter: Owen Nichols
currently, we run Build, then all <x>Test jobs in parallel (which takes ~5
hours), then all Benchmark<x> jobs (which takes ~5 hours).
Presumably the benchmarks were run after all tests, on the premise that
benchmarks are meaningless if the code is not correct. However, required PR
checks now prevent incorrect code from getting into develop in the first place,
and the remaining occasional failures are flaky, so it's rather arbitrary to
gate benchmarks on a lottery.
However, faster feedback has clear benefits, and cutting our CI pipeline from
10 hours to 5 hours seems like low-hanging fruit.
--