https://issues.apache.org/jira/browse/HBASE-21319?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=16652816#comment-16652816
 ] 

Duo Zhang commented on HBASE-21319:
-----------------------------------

I mean the nightly job, not the pre commit job...

In nightly job we will not pull out the flakey tests?

> The nightly jobs should run 'mvn test' with '-fn'
> -------------------------------------------------
>
>                 Key: HBASE-21319
>                 URL: https://issues.apache.org/jira/browse/HBASE-21319
>             Project: HBase
>          Issue Type: Improvement
>          Components: test
>            Reporter: Duo Zhang
>            Priority: Major
>
> For now, it will fail in the middle if there are failures. I think for a 
> nightly job we should run all the UTs.
> The nightly pipeline is complicated and uses yetus so I'm not sure how to fix 
> it...



--
This message was sent by Atlassian JIRA
(v7.6.3#76005)

Reply via email to