Hi,
Currently,Tear down and set-up is executed at pre and post execution of all
thread group. The purpose of thread group is to set-up or clear the resources.
In load testing or functional testing, set-up or clear the resources also
required at thread group level.
this can be done through a sampler, But in this case, many problems occurred.
1) For clean-up purpose, I have to continue test plan even if it fails.
2) By looking at test, I can not say that which are my test step and which are
my clean-up and set-up steps.
--