https://issues.apache.org/jira/browse/MESOS-8624?page=com.atlassian.jira.plugin.system.issuetabpanels:all-tabpanel
 ]

Meng Zhu reassigned MESOS-8624:
-------------------------------

    Shepherd: Greg Mann
    Assignee: Meng Zhu

> Agent task launch relies in-order future collect which `collect()` does not 
> support
> -----------------------------------------------------------------------------------
>
>                 Key: MESOS-8624
>                 URL: https://issues.apache.org/jira/browse/MESOS-8624
>             Project: Mesos
>          Issue Type: Bug
>    Affects Versions: 1.5.0
>            Reporter: Meng Zhu
>            Assignee: Meng Zhu
>            Priority: Critical
>
> In https://issues.apache.org/jira/browse/MESOS-1720, agent starts to rely on 
> in-order task launch between tasks using the same executor, i.e. tasks of the 
> same executor should be launched in the order the agent receives them. 
> Otherwise, failures like this ( 
> https://issues.apache.org/jira/browse/MESOS-8617?focusedCommentId=16382531&page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel#comment-16382531)
>  would occur.
> However, the two asynchronous steps (unschedule GC and task authorization) in 
> the agent task launch path use `collect()` which does not guarantees order 
> between different collect issued by the same actor. This will result in 
> out-of-order task launch and cause tasks being dropped or lost:
> https://github.com/apache/mesos/blob/32f6d4eec2724414e217875f4f7d3b2538db5381/src/slave/slave.cpp#L2888
> Based on disussion with [~chhsia0] and [~bmahler],  we should take an 
> explicit approach of using process::Sequence to
> ensure ordered task delivery (this would need to be done both in the master 
> and agent).



--
This message was sent by Atlassian JIRA
(v7.6.3#76005)

Reply via email to