Michael W Moser commented on NIFI-11162:
----------------------------------------

NiFi 2.0 will be able to support rolling upgrade of a cluster.  See NIFI-12016.

> When upgrading, rolling restart nodes to avoid service interruption
> -------------------------------------------------------------------
>
>                 Key: NIFI-11162
>                 URL: https://issues.apache.org/jira/browse/NIFI-11162
>             Project: Apache NiFi
>          Issue Type: Improvement
>          Components: Core Framework
>    Affects Versions: 1.20.0
>            Reporter: macdoor615
>            Priority: Major
>
> The current upgrade requires stopping all nodes at the same time, upgrading 
> all nodes, and then restarting all nodes, which will interrupt the service.
> It is recommended to support rolling upgrades, each node is stopped, 
> upgraded, and restarted one by one to avoid service interruption.
> Before all nodes are upgraded, the early version of the inter-connection 
> protocol is adopted between nodes. When all nodes are upgraded, the 
> inter-connection protocol will upgrade to the current version.



--