Matt Gilman updated NIFI-4969:
------------------------------
       Resolution: Fixed
    Fix Version/s: 1.6.0
           Status: Resolved  (was: Patch Available)

> Failed to import versioned flow when processor uses "Event Driven" scheduling
> -----------------------------------------------------------------------------
>
>                 Key: NIFI-4969
>                 URL: https://issues.apache.org/jira/browse/NIFI-4969
>             Project: Apache NiFi
>          Issue Type: Bug
>    Affects Versions: 1.5.0
>            Reporter: Bryan Bende
>            Assignee: Bryan Bende
>            Priority: Major
>             Fix For: 1.6.0
>
>
> Create a flow where a processor has scheduling strategy set to event-driven 
> with concurrent tasks set to 0. Start version control on the flow, and them 
> try to import a new process group using the flow from previous step.
> The error is because during import we set the concurrent tasks value before 
> the scheduling strategy, and StandardProcessorNode line 630 throws an 
> exception if the tasks is < 1 and strategy is not event driven.
> The exception also does not report any message so it is hard to figure out 
> what the issue is.



--