> When push-based shuffle is enabled, a stage may not complete when retried
> -------------------------------------------------------------------------
>
> Key: SPARK-38973
> URL: https://issues.apache.org/jira/browse/SPARK-38973
> Project: Spark
> Issue Type: Bug
> Components: Shuffle, Spark Core
> Affects Versions: 3.2.0
> Reporter: Chandni Singh
> Assignee: Chandni Singh
> Priority: Major
> Fix For: 3.3.0
>
>
> With push-based shuffle enabled and adaptive merge finalization, there are
> scenarios where a re-attempt of ShuffleMapStage may not complete.
> With Adaptive Merge Finalization, a stage may be triggered for finalization
> when it is in the below state:
> # The stage is *not* running ({*}not{*} in the _running_ set of the
> DAGScheduler) - had failed or canceled or waiting, and
> # The stage has no pending partitions (all the tasks completed at-least
> once).
> For such a stage when the finalization completes, the stage will still not be
> marked as {_}mergeFinalized{_}.
> The stage of the stage will be:
> * _stage.shuffleDependency.mergeFinalized = false_
> * _stage.shuffleDependency.getFinalizeTask = finalizeTask_
> * Merged statuses of the state are unregistered
>
> When the stage is resubmitted, the newer attempt of the stage will never
> complete even though its tasks may be completed. This is because the newer
> attempt of the stage will have {_}shuffleMergeEnabled = true{_}, since with
> the previous attempt the stage was never marked as {_}mergedFinalized{_}, and
> the _finalizeTask_ is present (from finalization attempt for previous stage
> attempt).
>
> So, when all the tasks of the newer attempt complete, then these conditions
> will be true:
> * stage will be running
> * There will be no pending partitions since all the tasks completed
> * _stage.shuffleDependency.shuffleMergeEnabled = true_
> * _stage.shuffleDependency.shuffleMergeFinalized = false_
> * _stage.shuffleDependency.getFinalizeTask_ is not empty
> This leads the DAGScheduler to try scheduling finalization and not trigger
> the completion of the Stage. However because of the last condition it never
> even schedules the finalization and the stage never completes.
--