https://issues.apache.org/jira/browse/TEZ-2967?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=15156294#comment-15156294
 ] 

Rohini Palaniswamy commented on TEZ-2967:
-----------------------------------------

bq. The Vertices table have a "First Task Start Time" along with the "Start 
time", wouldn't that work?
  No. When there are 20-80 vertices in a DAG cannot keep opening each vertex 
page to see when it actually started. The current vertex start time is useless 
as it is same as DAG start time. It needs to be replaced with when the vertex 
actually started running.

bq. Is it ok to make the duration change as part of Tez UI 2.
  Yes. But if it is easy to do, would be good to have it in Tez UI 1 as well. 



> Vertex start time should be that of first task start time in UI
> ---------------------------------------------------------------
>
>                 Key: TEZ-2967
>                 URL: https://issues.apache.org/jira/browse/TEZ-2967
>             Project: Apache Tez
>          Issue Type: Bug
>          Components: UI
>            Reporter: Rohini Palaniswamy
>            Assignee: Sreenath Somarajapuram
>
>   Currently it shows the vertex initialization time which is hardly of any 
> use.



--
This message was sent by Atlassian JIRA
(v6.3.4#6332)

Reply via email to