Hi,

I have been puzzling through some confusing behavior experienced in jBPM 5.1 
which I did not see in jBPM 5.0.

Specifically what I see is when the first iteration of a Multiple Instances 
task hits the end node in the multiple instances sub-flow the entire process is 
terminated.

I have verified this from stepping through the debugger and instrumenting my 
session with a listener to see which tasks are triggered, terminated etc.  What 
I see is a single iteration through the sub-flow in the mulitple instances 
graph followed by each subsequent iteration triggering but the process 
terminating before the other iterations even get started down their path.

I'm not setting up the flow any different than I would have in jBPM 5.0.

Also, in jBPM 5.0 I noticed that Custom Tasks did not behave properly in jBPM 
5.0, worked around by using a re-usable subflow task.  When stepping through in 
the debugger I see that subsequent iterations through the sub-flow seem to 
thing the custom task has triggered already.  Anybody know if this has been 
addressed in 5.1?

Still a big supporter!

Dave
--------------------------------------------------------------

Reply to this message by going to Community
[http://community.jboss.org/message/615029#615029]

Start a new discussion in jBPM at Community
[http://community.jboss.org/choose-container!input.jspa?contentType=1&containerType=14&container=2034]

_______________________________________________
jboss-user mailing list
[email protected]
https://lists.jboss.org/mailman/listinfo/jboss-user

Reply via email to