Hi Martin,

On Apr 14, 2012, at 11:19 AM, Martijn Verburg wrote:

> It's a hard one to guess this far out. My aim is to have the individual 
> projects run the testing but to provide volunteer testers from the various 
> user groups around the world.  So for example the Apache Tomcat team would 
> set a few days for testing and we'd provide 5-10 folks to help them execute 
> their specific test plan.
> 
> I'll need to get more feedback from the various project leads to see how long 
> they think it'll take (several of them had Java 7 test plans, so hopefully we 
> can get a rough guide).

Thanks for the details. For now I've made the assumption that four calendar 
weeks will be needed for the JUGs testing so I can come up with an M7 date. If 
the assumption turns out to not be valid after you've spoken to the project 
leads then I'll revisit the date. If you could let me know once you've had the 
chance to speak to the various project leads that would be great.

Kind regards,
Mathias