Hello Mike

> you mean you want test 2 to start 2 seconds after test 1 
> starts (a sort of 
> "ramping" up effect?).
Yep that is the thing i need (I think so) :)

Why I need such things:

Our hardware: 2x Linux virtual server, 4x apache-tomcat balanced by
mod_backhand.

We do a kind of authorization against a oracle-db.
t1. check of a "cardnumber" takes about 1.5 sec,
t2. after this check we do a "money" transaction. 1 sec
t3. costumer transaction commit or rollback ~0.5 sec

We have 100 test cards, and we have 100 test transaction(t1,t2,t3).
"We can't do 2 transactions(t1,t2,t3) for the same card at the same time."

So I am in need of something that starts the same transaction with ~ 3 sec
delay, because
We like to test ~100 concurrent autorizations.

Am I on the right way ? Or do I miss something ? Or is there another way ?


Regards lothar

Thx again for your response.




> -----Urspr�ngliche Nachricht-----
> Von: Mike Stover [mailto:[EMAIL PROTECTED]] 
> Gesendet: Mittwoch, 13. Juni 2001 14:26
> An: Egger Lothar; [EMAIL PROTECTED]
> Betreff: Re: Thx Mike - and some other questions....
> 
> 
> On Wednesday 13 June 2001 13:15, you wrote:
> > Hello
> >
> > Thanx Mike, for your response and the script. :)
> > it worked with the latest cvs checkout.
> >
> > Another question:
> >
> > We are testing servlets, the servlets a querying a oracle 
> db and the 
> > response is about 1.5 sec. I am in need to put some delay 
> between the 
> > test.
> >
> > Eg test1:
> > Query 100 urls
> >
> > Eg test 2:
> > Start 2 seconds later than test1 and query the same 100 urls
> >
> > Eg test 3:
> > Start 2 seconds later then test2 and so on .....
> >
> > Is this possible ?
> 
> I don't think so.  Do you mean you want test1 to start and 
> finish, then test 
> 2 to start and finish, and then 3, with a 2 second delay 
> between each?  Or do 
> you mean you want test 2 to start 2 seconds after test 1 
> starts (a sort of 
> "ramping" up effect?).
> 
> JMeter does not currently do either, however, writing a 
> looping controller 
> would not be difficult, and it could include a delay before starting 
> parameter to it.  This would allow you to do what I first 
> described.  Ramping 
> up and layering tests I would have to think about how to do....
> 
> >
> >
> > Regards
> > Lothar
> >
> > Thx again for your help
> >
> > 
> ---------------------------------------------------------------------
> > To unsubscribe, e-mail: [EMAIL PROTECTED]
> > For additional commands, e-mail: [EMAIL PROTECTED]
> 
> -- 
> Mike Stover
> [EMAIL PROTECTED]
> 

---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]
For additional commands, e-mail: [EMAIL PROTECTED]

Reply via email to