Calculating percentiles is resource intensive for JMeter, so the Aggregate
Report is not recommended when running a large number of threads.  But you
can always just record the sampler results and calculate the percentiles
after the test is over.  Here is a wikipedia link with the arithmetic info:
http://en.wikipedia.org/wiki/Percentile

Regards,

Matt C.

-----Original Message-----
From: Chen, Song [mailto:[EMAIL PROTECTED] 
Sent: Wednesday, May 02, 2007 9:14 PM
To: JMeter Users List
Subject: how to calculate the 99.9% Line

Hello,
  In aggregate report only 90% Line is shown. Can we gather the 99% and
99.9% Line? Anyone knows the arithmetic, or which JMeter sourcefile to
modify?

Thanks

Chen Song





---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]
For additional commands, e-mail: [EMAIL PROTECTED]

Reply via email to