Did u manipulate with start & end timings, I mean you have started your
load test script and after that you have stop it and changed the revised
timings and executed again?

If it's the case then some times JMeter doesn't consider latest saved
values.

Rushabh 


-----Original Message-----
From: Anjaneyulu Aerrolla [mailto:[EMAIL PROTECTED] 
Sent: Saturday, June 16, 2007 8:18 PM
To: [email protected]
Subject: J-Meter Scheduler wont start on Specified time.

Hi 
 
I'm trying to schedule the run using the thread group's scheduler option

Following are the values for the thread group.
 
Number of Threads: 1
Ramp up Period: 1
Loop Count Forever checked 
Schedule checked
Start Time: 2007/06/16 12:10:12
End Time: 2007/06/16 12:15:12
And not given any value for duration and Startup delay 
 
According to above settings it should start at 12:10:12 and run for
5mins and end at 12:15:12, but for my surprise 
The test never starts, is there anything wrong I'm doing, or something
missing?
 
I'm running j-meter version 2.2 on Windows XP, with JDK 1.5.0.8
 
Thanks 
_________________________________________________________
Anjan | Associate Technology | Sapient | Bangalore, India
[EMAIL PROTECTED] | +91 80 41047003 (work) | +91 9886619293 (cell)
 

---------------------------------------------------------------------
To unsubscribe, e-mail: [EMAIL PROTECTED]
For additional commands, e-mail: [EMAIL PROTECTED]

Reply via email to