On 02/14/2011 10:56 AM, Jing Ning wrote:
> Hi,
> 
> When I use the JMeter to create test plans, some times I need to merge two 
> test plans to one new test plan, but I found JMeter doesn't support copying 
> test elements between test plans, you can only copy and paste the elements 
> within the test plan. Did any of you have the same trouble?
> 
> BRs,
> Ning Jing

Hi,

you may want to try to save a partial Test Plan and load it into the
other Plan.

Mark all thread groups in Plan A, Save as ..., then load the resulting
JMX file while your target Plan is open. I'm not sure if some other step
is necessary, as I've never fiddled with partial Test Plans.

HTH,
Felix

---------------------------------------------------------------------
To unsubscribe, e-mail: [email protected]
For additional commands, e-mail: [email protected]

Reply via email to