Hello everybody, Here is the timeline I plan to follow for the 18.05 release:
* April 20 - "Soft" feature freeze, nothing big or with high risk of side-effects will be included into the final release if not marked as Passed QA (and the converse is false). * April 27 - "Hard" feature freeze, nothing considered as an enhancement will be pushed if not marked as Passed QA (exception will be made for tests). * May 4 - String freeze, draft of release notes published * May 11 - Only bugfixes considered as major, critical or blocker will be pushed * May 22 - Final Release Any comments or change requests? Regards, Jonathan _______________________________________________ Koha mailing list http://koha-community.org [email protected] https://lists.katipo.co.nz/mailman/listinfo/koha

