> ...I've asked around
> whether it is possible to deliver the contents of one ARC case with
> multiple putbacks but the answers were a bit "fuzzy"

Speaking not as an ARC member, but rather as a CRT Advocate and former 
Tech Lead:

Standard expectation is that a single ARC case will be integrated as a 
single unit.

If you intend anything else, either because a coordinated delivery is 
necessary, or you plan to stage multiple deliveries for different phases 
of the work, then it should be called out explicitly in the ARC case 
materials.

If I evaluate a project or RTI, and find that it's only delivering a 
subset of the work specified in the ARC case materials, and that this 
was not made explicit when it was reviewed by the ARC, then I typically 
ask the submitter to send a note to the case log, describing what 
they're doing and why, and giving the members a chance to comment.

If I have to dig to find this information, I get a little bit grumpy. 
Ie if you're only delivering a subset of the case materials, please 
spell it out clearly in the RTI.  Otherwise it feels like you've either 
been careless, or that you're trying to be sneaky.  (Neither of which is 
usually true, but your advocate doesn't always have all of the 
information that you have...)

--Mark

Reply via email to