On Wed, 21 Dec 2016, Jo-Philipp Wich wrote:
- set grace period of 5 days to identify and fix blockers
<snip>
day 16 - extend grace period by 5 days until blockers are resolved
As a practical matter, make these 7 days rather than 5 days. the shift between
the work-week and the release schedule will cause problems both for devs and
testers.
- When do we want to branch?
Personally I'd like to branch before Christmas so that we can use the
free time for building images (it takes about 8 days and ~2TB of space
to build all targets and all packages).
how big is the build farm? how much hardware would people need to donate to
reduce this significantly (1-2 days for example)?
David Lang