On 07/11/2012 03:39 PM, Noel Grandin wrote:
I'm sitting here with a 6-core monster of a machine, and watching it
idle away
(top says 90% idle, iotop says basically nothing is happening)
as it gently processes the [SCK] stages of "make subsequentcheck".
I've tried cranking up --with-max-jobs to 18 and --with-num-cpus to 12,
but that doesn't seem to be helping much.
I think what might be happening is that longer-running tests are towards
the end, and I'm suffering from a "long tail" effect.
I think it ought to be possible to speed this up a bit by re-ordering
the longer running stuff towards the beginning.
Where in the build scripts should I look to change this ordering?
IIUC, the order the tests are run is implicit in how make orders
execution of targets. (From my experience, the toolkit/unoapi test is
rather long-running and somewhat unfortunately gets scheduled towards
the end.)
We used to have a CHECK_PARALLELISM variable to be able to specify the
parallelism of executing those tests independent of
--with-max-jobs/--with-num-cpus (as each such test tends to produce
little load, so it can be beneficial to run ~many of them per cpu), but
that apparently got lost with
<http://cgit.freedesktop.org/libreoffice/core/commit/?id=8a310e3521db1f9a15a7ec32b3171c4969c461be>
"moved some more targets to gbuild."
Stephan