Key Points for wider discussion
===============================

 11.08 Release is out of the door.
 11.09 BPs are here: https://launchpad.net/linaro-android/+milestone/11.09

Team Highlights
===============================
 igloocommunity (Snowball) bugs can now be linked to from launchpad.
 Lots of testing took place in the release week.

Miscellaneous
===============================
 Imminent activities in management and administration:
  - Guidelines for Gerrit review work.
  - Get boards for the Automated testing.
  - Join forces with Validation to assert Automated testing can be rolled out.
  - Assert that toolchain and product release schedules are not colliding.
 bhoj has started. He will be TI PoC and is based in Bangalore.
 fgiff will be on vacation 2011-09-26 to 2011-10-07

_______________________________________________
linaro-dev mailing list
linaro-dev@lists.linaro.org
http://lists.linaro.org/mailman/listinfo/linaro-dev

Reply via email to