On 13 March 2012 03:00, Mounir Bsaibes <[email protected]> wrote: > David, > Looks good. > The Work Packages is a new terminology, maybe a little more details about > it. > For example: Work Package can be a Work Items block that can be delivered > in one month. > Some of the Working Groups use a single blueprint with multiple WI's blocks > each WI's block to be delivered in one month.
I don't like adding new terminology. A blueprint should be achievable in a month and should be used instead of work item blocks. Work packages can be blueprint headlines - it doesn't matter that these will be refined and perhaps split into the final blueprints as long as there is tracability. -- Michael _______________________________________________ Mailing list: https://launchpad.net/~linaro-project-management Post to : [email protected] Unsubscribe : https://launchpad.net/~linaro-project-management More help : https://help.launchpad.net/ListHelp