On Wed, Jun 13, 2012 at 8:51 PM, David Zinman <[email protected]> wrote: > Regretfully this summary is very late. > > The Linaro 12.05 delivery cycle was fast and furious with Connect Q2.12, end > of > quarter and delivery all occurring in the same week. > > During this 2012.05 Linaro Connect, much of the effort was focused on: > * ARM big.LITTLE implementation and testing > * Performance improvements > * Linaro-linux baseline > * Release process streamlining > > Delivery highlights can be seen at http://www.linaro.org/downloads/1205#tab1 > > > Platform Blueprints > ---------------------------- > The number of blueprints that missed the cycle: > Android 18 out of 30 > Developer Platform 6 out of 18 > Infrastructure 5 out of 10 > Lava 5 out of 18
Here, I am currently not sure what to do with those numbers. Basically, I am not so much worried about low/medium blueprints that didn't get delivered. Any way we could get those numbers broken down by priority? Or just a view on our delivery rates for essential and high blueprints? -- Alexander Sack Technical Director, Linaro Platform Teams http://www.linaro.org | Open source software for ARM SoCs http://twitter.com/#!/linaroorg - http://www.linaro.org/linaro-blog _______________________________________________ Mailing list: https://launchpad.net/~linaro-project-management Post to : [email protected] Unsubscribe : https://launchpad.net/~linaro-project-management More help : https://help.launchpad.net/ListHelp