On Wed, Jan 9, 2013 at 1:49 PM, Matthew Gretton-Dann
<[email protected]> wrote:
> Paul,
>
> This sounds good.  In particular:
>
>
> On 09/01/13 12:10, Paul Sokolovsky wrote:
>>
>> 3. Once review is passed (hopefully within a week or shorter), we
>> schedule a date for merging and deployment, subject to constraint of
>> TCWG release schedule.
>
>
> Completing reviews so deployment can happen in the week beginning 21st Jan
> is good for us (as you suggest), as this is the week after release and gives
> two weeks to sort any issues out before we start merges again.
>

And remember: ensure that we can easily go back to old setup in case
things fall apart and put our release at risk :)

> Thanks,
>
> Matt
>
>
> --
> Matthew Gretton-Dann
> Toolchain Working Group, Linaro



-- 
Alexander Sack
Director, Linaro Platform Engineering
http://www.linaro.org | Open source software for ARM SoCs
http://twitter.com/#!/linaroorg - http://www.linaro.org/linaro-blog