Routine 20-year resurfacing of runway 5-23 will be done in two parts, starting 
with the southern end starting in June of this Summer.  The paving trucks will 
be routed along Virginia road in Lincoln to the Airport road, and then route 2A 
to route 128. The paving trucks will be operating for 20 days during a 37 day 
period (daytime Monday-Friday only) and there will be about 100 truck loads (50 
round trips) for each of those 20 days. The northern end of the runway will be 
paved next year, but the truck traffic will be routed through Bedford. The 
Lincoln police department will be responsible for project  traffic safety.

This will be a major disruption for residents in the affected part of Virginia 
road but once it is complete this operation will not be repeated for 20 years.

There will also be some changes to flight patterns resulting from the month 
long closure of this runway so some residents will hear more flights and some 
will hear less during this period. At the end of the project it is expected 
that flight patterns will return to normal.

https://thebedfordcitizen.org/2023/03/bedford-escapes-most-of-this-summers-runway-resurfacing/



-- 
The LincolnTalk mailing list.
To post, send mail to [email protected].
Browse the archives at https://pairlist9.pair.net/mailman/private/lincoln/.
Change your subscription settings at 
https://pairlist9.pair.net/mailman/listinfo/lincoln.

Reply via email to