David C. wrote:

> “cutting $2.3M out of the project would require a complete redesign
> (estimated cost $1.5M to $2.0M)”
>
> This stretches the bounds of plausibility. Anyone familiar with
> construction projects knows that cost-cutting trade-offs are often
> necessary, and rarely do they require paying full architectural fees all
> over again.
>
There's not a smooth linear slider where we can just "uncheck boxes" and
costs come down.

Sometimes, you can't materially reduce scope or cut costs without
triggering a redesign.  For example, if you need to materially reduce
costs, that may trigger a footprint reduction, which may trigger a room
reduction, which triggers a layout change, which triggers a roof change,
etc.  If it's already highly constrained (as this project is), you may need
to look at a couple of conceptual designs before committing to a new
redesign, review with all the stakeholders, renegotiate tradeoffs, etc.
And, because of the municipal process, we need to generate a new full set
of design documents so that bidders have enough detail to submit new bids.

The CCBC-provided redesign cost estimate may be "conservative", but it's
not surprising if it's close to a design-from-scratch cost since a redesign
means going back to nearly the beginning.

“and a delayed timeline, resulting in further escalated costs ($1.5M to
> $2.0M)”
>
> Have they never heard of the time value of money? I’d rather see my taxes
> levied two years from now than today. Delaying the project means capital
> remains available for more productive uses. Even if the funds are already
> allocated, they would be earning interest—likely 4–5%. Any escalation
> estimate should be offset by that. Moreover, our record for predicting
> escalation is weak at best. We should avoid baseless speculation.
>
To clarify:  the majority of funds (~$16m) would be bonded, and that would
happen *after* we are "go flight!" with an accepted bid, etc.  At that
point, we're paying interest on those funds and MA anti-arbitrage laws
prevent us from earning more interest/return than we're paying on float.
Generally, if bonding is involved, we can't arbitrage away cost escalations
in any meaningful way.

Do residents prefer to pay escalated costs in ~2 years *vs* current costs,
as you suggest?  Maybe; I'd be very surprised. That's why we vote.

One if-you-think-community-centers-are-expensive-try-two-weddings
resident's view,

-andy
-- 
The LincolnTalk mailing list.
To post, send mail to [email protected].
Browse the archives at https://pairlist9.pair.net/mailman/private/lincoln/.
Change your subscription settings at 
https://pairlist9.pair.net/mailman/listinfo/lincoln.

Reply via email to