Essentially we don't have a spokes person, someone directly involved in the
project available to answer questions and provide guidance.

On Fri, Jul 25, 2025, 7:55 AM Edward Young via Lincoln <
[email protected]> wrote:

> A progress report from the Town about the water main project would be very
> helpful at this point, including an estimate for the completion date for
> the project.
>
> Hopefully, before school starts.
>
> This is because a number of things seem to have changed from the Town's
> initial projections in regard to timeframe and road closures.
>
> Members of the crew tell me that they typically lay about 6 sections of 22
> foot pipe per 8 hour shift, or 132 feet per day. From Reservoir Road to the
> flower pot is approximately half a mile, and another half mile to Ballfield
> Road, for a total of about 5,200 running feet. Divided by 132 feet per
> shift, that’s about 40 working days, or 8 weeks, taking the pipe-laying
> phase of the project to late September, after which they’ll need to hook
> all the houses up to finish the job.
>
> The workers indicate that the project was significantly delayed by the
> unexpected complexity of Lincoln’s antiquated piping system, causing them
> to have to prepare far more temporary lines than would be expected before
> they could proceed with the replacement pipes.
>
> The foregoing is based entirely on casual conversations with those workers
> whom I’ve run into out in the road itself, not the engineers or top brass
> who may know better than they what the status of the project is.
>
> The workers also indicate that the original expectation that one-lane road
> closures would be common, and complete closures rare, has been superseded
> by a determination by the Lincoln Police that single lane closures are too
> dangerous for the workers under OSHA, at least until the project reaches
> the flower pot, due to the narrowness of Bedford Road as compared with
> Lincoln Road.
>
> As I said, the foregoing is just what the guys in the trenches have told
> me; it would be nice to have an official progress report.
>
> As well as an explanation why the configuration of the existing piping
> wasn’t initially understood and why it was initially thought that one lane
> closures would be safe. After all, the width of the road hasn’t changed.
>
> Respectfully,
>
> Ned Young
> 41Bedford Road
> (thankfully not in the construction area ourselves)
> --
> The LincolnTalk mailing list.
> To post, send mail to [email protected].
> Browse the archives at https://pairlist9.pair.net/mailman/private/lincoln/
> .
> Change your subscription settings at
> https://pairlist9.pair.net/mailman/listinfo/lincoln.
>
>
-- 
The LincolnTalk mailing list.
To post, send mail to [email protected].
Browse the archives at https://pairlist9.pair.net/mailman/private/lincoln/.
Change your subscription settings at 
https://pairlist9.pair.net/mailman/listinfo/lincoln.

Reply via email to