(2/2)

... And then there are the operating costs.

It is usually a telco’s ongoing operating costs, not its capital costs, that 
determine its cashflow performance. Telcos constantly strive to reduce 
operating costs by simplifying their product set and associated processes. With 
the change to the MTM we have gone in the other direction. Using multiple 
technologies increases the complexity of the required IT systems, the 
maintenance costs, the holding costs for spare parts, the training costs and 
the overhead costs.

This point was admitted in April 2018 by the then CEO of NBN Co, Bill Morrow, 
in his paper published by NBN Co. He stated that the MTM model meant lower 
speeds, more faults and higher maintenance costs than Labor’s FTTP-based 
network. (He was, of course, also obliged to say that the original FTTP network 
would have cost more to build than the MTM. But this claim was, as we will soon 
see, not supported by the facts.)

It is also an unfortunate reality that the renegotiated Telstra deal put in 
place by Turnbull and Morrow has increased NBN Co’s costs. In the original 
deal, responsibility to make Telstra’s pit and duct infrastructure “fit for 
purpose” was squarely with Telstra. But under the deal renegotiated for the 
MTM, that responsibility, including any asbestos problems, was transferred to 
NBN Co – and by extension to the Australian taxpayer.

>From every angle, the decision to use the old copper and HFC (pay-TV) cables 
>has turned out much worse than the Coalition’s plan anticipated. There were 
>plenty of warnings. A senior Telstra manager suggested in 2003 that the copper 
>phone network would need to be replaced within 15 years, saying the ageing 
>lines are now at “five minutes to midnight”. He also indicated the use of ADSL 
>was the “last sweat” of revenue that could be wrung out of the old copper 
>network.

Given that NBN Co had purchased more than 27,000 kilometres of new copper cable 
as of mid November 2018, in some cases to provide a barely acceptable service, 
the Telstra manager has been proven correct.

A similar story has unfolded with the attempts to use the HFC cable networks 
built by Optus and Telstra. In 2010, the team at NBN Co evaluated the possible 
use of these networks as part of the NBN. They rapidly came to the conclusion 
that this was not a viable option: at that time, they believed the best option 
was to use neither of the HFC networks, and instead to financially compensate 
Telstra and Optus for progressively transferring their HFC broadband customers 
onto the FTTP-based NBN. In fact, the NBN Co team took only a few weeks to come 
to the conclusion that Optus’s HFC network was unusable for hi-speed broadband 
without a major investment in remediation and upgrades.

This conclusion was heavily criticised by Turnbull, and he subsequently 
directed NBN Co to make use of both HFC networks as part of the MTM when the 
Coalition formed government in 2013; an interesting directive, given the claims 
of adopting a “technology neutral” approach. By 2015 it was evident that the 
Optus HFC network was indeed unusable and the 450,000 NBN services that 
Turnbull had projected would be delivered using the Optus HFC network were 
reduced to the 25,000 that had already been deployed.

The picture was somewhat better with the Telstra HFC network; nevertheless the 
number of NBN services to be provided using this network has decreased from 
initial estimates, while the implementation time and costs have increased 
dramatically. As recently as October 2018, the CEO of NBN Co advised Senate 
Estimates that close to a billion dollars of the peak funding increase are due 
to the “HFC pause” to fix problems and to “optimise” the HFC network.

There are now no easy solutions to these revenue and operations challenges, and 
to the impact they are going to have on NBN Co’s finances. The cash already 
spent on implementing the MTM cannot be recovered.

These woes, especially the problem with future cash flow, are exacerbated by 
NBN Co’s inability to participate significantly in 5G rollouts across 
Australia. Telcos understand that a deep-fibre deployment is vital to underpin 
5G coverage, and Labor’s original FTTP plan would have been able to play a 
complementary role in the deployment of 5G. This was anticipated by NBN Co’s 
management when they allocated the number of fibres to each area as part of the 
original FTTP network planning.

If the deep-fibre FTTP network had been completed, NBN Co could now be 
developing another important wholesale revenue stream by offering wholesale 
fibre connections to the large number of 5G mobile cell sites needed. With the 
MTM, using the old copper infrastructure, this revenue opportunity has largely 
evaporated. This has turned 5G from a potential revenue opportunity for NBN Co 
into a competitive threat.

Despite the MTM strategy’s evident failures, Turnbull and the Coalition were 
very successful at convincing the media and the general public that the 
original NBN would have been much worse. The misinformation campaign waged 
almost from the start was very effective. One early experience I had as CEO 
illustrates this.

I was visiting a very senior public servant in Canberra to provide him with an 
update on the NBN. He was an intelligent and informed individual, but one who 
had no direct day-to-day involvement in the NBN. After we had exchanged 
pleasantries he said, “Mike, can you tell me why the NBN is so over budget?” My 
response was “Why do you think it’s over budget?” I then showed him the data as 
to how the project was actually progressing.

It was running about nine months behind the original schedule because of the 
time it took to complete the highly complex, but advantageous, deal with 
Telstra. However, the capital costs, the operating costs, the peak funding and 
the internal rate of return were virtually unchanged from the original 
estimates.

He reflected for a minute and said, almost to himself, “Why did I think it was 
over budget?”

It was because on an almost daily basis he had read or heard that the NBN was 
way behind schedule and way over budget – a good example of that famous adage 
variously attributed to Vladimir Lenin or Joseph Goebbels: “A lie told often 
enough becomes the truth.”

This technique is still being used with similar effect today by the current 
minister for communications, Mitch Fifield, and other members of the Coalition. 
When asked about the delays and cost overruns of the MTM, their response is to 
repeat ad nauseam that the original FTTP-based NBN would cost $30 billion more 
in peak funding and take six to eight years longer than the MTM. This is 
demonstrably false.

The reason that ministers have continued to repeat this claim is fairly 
obvious. The increase in the MTM peak funding and deployment times created 
quite a problem for the Coalition.

Their “solution” was to claim that the original NBN was always going to be more 
expensive and take much longer than the estimates made in September 2013 by NBN 
Co. (Those estimates showed a peak funding of $45 billion and completion by the 
end of 2021.)

The range of peak funding costs for the FTTP NBN claimed by Turnbull and then 
Mitch Fifield went from $94 billion in April 2013, to $64–73 billion in 
December 2013, to the $74–84 billion estimate made by NBN Co in August 2015.

The $94 billion figure included in the April 2013 Coalition policy document was 
a complete work of fiction. In fact, the Strategic Review initiated by Turnbull 
very soon after the 2013 election could not support the $94 billion number, 
even though its authors did their best to inflate the peak funding requirement 
of Labor’s FTTP NBN.

One would assume NBN Co could be trusted to make an accurate estimate. In its 
corporate plan for 2016, NBN Co says, “Management estimates that an all-FTTP 
fixed-line rollout could be completed by 2026 but possibly as late as 2028, 
with a peak funding range of $74–84 billion (vs. $46–56 billion for MTM)”. This 
statement became the basis for the answer given by Fifield to every question 
asked about the network: that Labor’s original NBN would have taken six to 
eight years longer and been $30 billion more expensive than the current MTM.

But as Bill Morrow, NBN Co’s then CEO, admitted in a Senate Estimates hearing 
in October 2015, the analysis performed by NBN Co did not attempt to estimate 
the peak funding and timing for a continuation of the FTTP-based NBN. Instead, 
they were asked by the government to predict the costs and timing of winding 
down the MTM and restarting the FTTP NBN – after two years of cost blowouts, 
commitments and delays with the MTM.

It is clear the $74–$84 billion peak funding and the calculation that it would 
take six to eight years longer was a nonsense concocted to allow the spurious 
argument that the original NBN plan would have been even more expensive and 
taken much longer to complete than the delayed and very costly Coalition 
alternative.

Not only did NBN Co make its estimate based on a restart rather than a 
continuation of the original NBN, they also made an even more egregious 
assumption: that there would be no significant reductions in the 
cost-per-premises FTTP fibre rollout over the life of the project. The original 
management team planned for a reduction of approximately 25 to 30 per cent over 
the eight-year life of the project. This is what was built into the corporate 
plan, which resulted in a peak funding cost of $45 billion. The new management 
team appointed by Turnbull, and the board he installed, assumed there would be 
no reduction in rollout costs over the life of the project. In fact NBN Co’s 
2018 corporate plan continues to show the same $4400 for the FTTP 
cost-per-premises that it quoted back in 2013.

The difference in total costs, from disregarding this reduction, is enormous. 
One has only to remember that the cost-per-premises figure is multiplied by 10 
million, the number of services to be completed by the end of the NBN build. 
This sleight of hand added billions of dollars in capital, interest and peak 
funding costs to the projected cost of the original FTTP NBN.

This of course raises the question: Could the 25 to 30 per cent cost reduction 
assumed by NBN Co, while I was CEO, have been achieved? Was this a reasonable 
assumption?

The answer is a resounding “yes”. Telcos all around the world have been 
reporting major reductions in fibre rollout costs over the past several years, 
due to advances in technology and practices. A comparison close to home is that 
of the largest FTTP builder in New Zealand, Chorus, which reported a 44 per 
cent reduction in per-premises costs over the last few years to 2017. This 
makes a mockery of NBN Co’s continued quoting of the same $4400 per-premises 
figure.

Given the complexity of all of this information, it is little wonder that the 
average person has problems sorting out fact from fiction concerning the 
original NBN. This is also why Turnbull as communications minister was so 
effective in “recasting” the numbers to support his assertions, and to seem, as 
usual, so erudite and plausible as he did so.

It is surprising, however, that Turnbull’s financial and technical credibility 
were not severely damaged when his assertions were blown out of the water by 
his own team only 12 weeks after he became minister. Remember: in April 2013, 
he said that his MTM would cost $29.5 billion, and all premises would be 
connected to the NBN by 2016 – he was $21.4 billion and four years off target.

It is also surprising that Turnbull persisted with his wildly optimistic 
estimates, when he must have been getting advice from many directions that the 
time frames and costs were not realistic. I advised him, in September 2013 in a 
meeting he requested at his Edgecliff electorate office, that it would take a 
long time and much effort to renegotiate the Telstra deal, as he had very 
little leverage. His response was one of quiet mirth. He was very confident it 
would all be straightforward.

It did turn out to be straightforward – for Telstra. NBN Co ended up with much 
of the responsibility for making the infrastructure Telstra was leasing fit for 
purpose. This was why Telstra’s CEO could say that the new deal was 
“unquestionably better for shareholders”. In other words, the deal negotiated 
by Turnbull was unquestionably worse for taxpayers.

While the average person may not follow all the financial and technical details 
of the NBN, most people do suspect that something has gone badly wrong with 
what was a popular and greatly needed national infrastructure project. They can 
also spot when an “independent report” is plainly wrong, such as when the 2014 
Vertigan Review, authored by a panel hand-picked by Turnbull, made the somewhat 
odd statement that a broadband connection with a peak rate of 15 megabits per 
second would be sufficient for 50 per cent of households in 2023. Even NBN Co 
CEO Bill Morrow thought this was a little “curious”.

Moreover, people know that it is incredibly short-sighted to spend billions of 
dollars to build a major piece of national infrastructure that just about meets 
today’s demand, but doesn’t allow for any significant growth in that demand 
over the next 10 or 20 years without very large upgrade costs.

It has taken several years for a clearer picture to emerge, but we now know the 
decision to change to the MTM was thoroughly flawed – and the network 
performance and NBN Co’s financials demonstrate this. The MTM network costs 
more and does less.

The nation will be bearing the consequences of that decision for years to come 
in an area that is critical to its long-term future.

Betting tens of billions of taxpayer dollars on a myopic, expensive and 
backward-looking network based on copper, as the Coalition has done – while the 
world was moving away from copper and embracing optical fibre – was a huge 
miscalculation. It was not driven by a sophisticated analysis of the best 
technology choices for Australia’s NBN, but by ideology and politics. As Paddy 
Manning observed in his 2015 biography of Turnbull, Tony Abbott was intent on 
killing off the NBN if the Coalition won government in 2013, and Turnbull 
believed the Labor plan for the NBN was flying in the face of 30 years of 
governments exiting from operating businesses.

The fact that such a huge amount of money has been invested in 
performance-limited MTM technologies means that a writedown of these 
investments is almost a certainty.

Unfortunately, and contrary to what is sometimes suggested, writing down the 
value of these assets will not improve NBN Co’s cash flow. And if NBN Co were 
to accede to the calls for significant reductions in NBN wholesale prices its 
cash flow would be further affected.

These calls are being made in spite of the fact that telecommunications costs, 
including mobile and fixed broadband, have decreased by 6 per cent since 1990 
whereas electricity costs have increased by more than 200 per cent, water by 
more than 150 per cent and the consumer price index by more than 60 per cent.

All of this highlights the challenges for any incoming government to find a 
viable financial path forward for NBN Co. With the amount of taxpayer money 
sunk into deficient network assets, the increases in operating costs, and the 
now limited opportunities for revenue increases, the options for the NBN are 
quite constrained.

Even so, an incoming government will need to find a way to improve the NBN over 
time, given the importance of ubiquitous high-speed and high-capacity 
broadband. We can only hope that sensible options can be identified to allow 
the customer performance and financial viability of the NBN to be restored, 
after the disastrous infrastructure changes and misleading politicking that 
have dogged such an essential national project.

Looking back on the experience and challenges of starting up a huge government 
enterprise in a technically complex area, and which, from the very start, was 
operating in a politically charged environment, there is one lesson that stands 
out: the need to maintain an undistracted focus on the objectives set for the 
organisation undertaking a project such as the NBN. This requires a discipline 
on the part of the government in setting and maintaining the objectives, an 
operating company staffed by experienced people who understand the business 
they are in, and a governance structure that allows fast and efficient 
decision-making.

In the early days of the NBN, the employees displayed a passion for and 
commitment to the project because they knew they were part of something that 
would be of lasting benefit to the nation. They did not need to be motivated by 
financial incentives and bonuses because they were sufficiently energised by 
the project itself. I believe that if a government could ever set a new path 
for the NBN, then that same spirit could again be leveraged to deliver a 
broadband network that will truly meet the long-term needs of the Australian 
public.

Michael Quigley

Michael Quigley worked for 36 years at Alcatel, including as COO, and was the 
CEO of NBN Co for its first four years.


_______________________________________________
Link mailing list
[email protected]
http://mailman.anu.edu.au/mailman/listinfo/link

Reply via email to