Hi Clément,
I tried to specify tasks like this: "-s task1,task2"
Unfortunately, task2 is still executed first. Is it a bug?
Thanks
Max
Clément OUDOT <[email protected]> a écrit :
2012/11/13 Maxime Pelletier <[email protected]>
Hi,
When I start LSC with "-c all" option on a configuration containing 2
tasks, how could I know which task will be executed first? Or is there a
way to specify which one to execute first?
I thought that it would execute in the order they appear in lsc.xml file,
but I had one case where the second one is executed first.
Thanks in advance.
You can try to specify tasks like this : -c task1,task2
Clément.