Attendees
Andy Connolly
Jacek Becla
Ray Plante
Cristina Beldica
Russell Owen
Kirk Borne
Jeff Kantor

Cost Estimate Status
Database sizes will be reworked with Tim/Kem view of how close to galactic
plane we go to, not splitting the object tables by stars and galaxies,
adopting Zeljko¹s suggestion regarding time information per frame for
galaxies (like stars) and 50% for spare attributes not yet identified.  The
cost estimates for disk space will be updated with this by end of this week.

Disk I/O for low volume queries is done, now working on high volume ones.
Once this is finished, this will also be used to update the disk cost
estimates.  Note that current queries are on catalogs only, not image
archive.

Reference Design Baseline/Review
There will be a review held before the August 24 freeze, either same week or
week before.  We will need to update UML and create graphics describing the
reference design for this review.  The goal will be to have draft graphics
and supporting tables that would ultimately go into the MREFC proposal.
Think on the order of 15 graphics and 10 tables.

Discussion of SVN repository structure
Agreed to move ahead with Russell¹s proposed scheme for DC1, Tim can comment
when he returns.  This is for DC1 only, longer term issues to consider:
- Multiple languages (C++, Java, Python)
- Baselines  that vary by facility
- Ensure that we can ³slice off² part of our software easily without taking
everything

Coverage for LSST PM Telecon this Thursday ­ Ray will cover it for DM