The weekly Data Management Project Manager's Online Meeting was conducted on
Friday, August 8, at the usual time and place (10:00am PDT/PST, dial-in is
866 330 1200 passcode 300 2363, video is the NOAO bridge at IP
140.252.1.34).

Attendees:
Ray Plante
Cristina Beldica
Deborah Levine
Jeff Kantor

Agenda:

Inter-group topics (Telescope & Site, Camera, System Engineering)
Camera Input: 
1.  Study sensors coming out of fab within a month
2.  focal plane curvature update by Seppala on the 16th during the normal
camera meeting
3.  starting to develop break-outs for the camera collaboration meeting
September 18th
4.  working on DOE budgets and white paper for submission at the end of
August 

Reference Design Review - Schedule and rough outline sent, Jeff will send
more detailed outline/template out early next week

Cost Estimates - 
AC labor still showing old levels in latest import into Primavera, Cristina
to validate current spreadsheet that is in docushare.  Increase from 97 to
100 TF at AC is already handled by 1 year slip in MREFC start, so no changes
at this time.  CPU price/performance trends used at Mtn/Base and AC are
different, need to resolve ASAP, no later than Monday.  Will discuss at
TechAssessWG.  IPAC now working on down-scope estimate to fit within targets
set by Jeff, should be ready today.

DC1 - 
Readiness to start Stage 2: Ray will verify starting today, notify Jeff if
issues.  Met with SDSC on SRB/Stage 1 re-run, SDSC are getting direct access
to the environment to analyze it.  NCSA have reserved next week on TG for
re-run, will depend on progress.

Administrative - 
Travel budgets for the rest of FY06 are tight, try to limit travel
Auditor comments on Monthly Reports - Cristina to continue saving emails and
to annotate report with date that individual institutions submitted their
reports.