1. First outage - Saturday, 11/25/17, from 7:00am - 1:00pm 2. Second outage - Saturday, 1/13/18, from 7:00am - 5:00pm
The plan is to shutdown the evening before and wait until the power is back and stable to bring the mirror back up. Please plan accordingly. The gist is that when we had that major power outage about 8 months ago, the transformer feeding HIG blew up. The new transformer has finally been manufactured (transformers are custom built) and the contractor needs two days to install the new transformer and to swap over the cables feeding the building. /brian chee -- ******************************************** University of Hawaii SOEST Advanced Network Computing Laboratory (ANCL) Brian Chee <c...@hawaii.edu> 2525 Correa Road, HIG 500 Honolulu, HI 96822 Office: 808-956-5797 _______________________________________________ LUAU@lists.freesoftwarehawaii.org mailing list http://lists.freesoftwarehawaii.org/listinfo.cgi/luau-freesoftwarehawaii.org