Hi Joe,

I would think you'd need to commit the table fairly frequently, or better
yet, issue a "Set Table ...FastEdit On Undo Off" before adding data.
Otherwise the temporary transaction may become to large. And in such a case
it's quite unneccessary.

Best regards / Med venlig hilsen
Lars Nielsen

**********************************************************
Lars Nielsen                                [EMAIL PROTECTED]
Senior Programmer, MapXtreme iGIS Specialist
Kampsax/MapInfo, Odense              http://www.mapinfo.dk
Authorized MapInfo Distributor in Denmark & Norway
Address: Rugaardsvej 55, DK-5000 Odense C
Telephone: +45 6313-5000           Facsimile +45 6313-5090
**********************************************************



                                                                                       
                                            
                    Joe Dineen                                                         
                                            
                    <[EMAIL PROTECTED]>               Til:    
[EMAIL PROTECTED]                                 
                    Sendt af:                            cc:                           
                                            
                    [EMAIL PROTECTED]        Vedr.:  MI-L Problem with 
MapInfo automation                              
                    onsmag.com                                                         
                                            
                                                                                       
                                            
                                                                                       
                                            
                    18-09-01 13:53                                                     
                                            
                    Besvar venligst til Joe                                            
                                            
                    Dineen                                                             
                                            
                                                                                       
                                            
                                                                                       
                                            



Hi
    I have recently joined a team developing a GIS based database
application.
Anyway we have a routine to export data to MI using MI automation. MI is
run
in the background using GetObject and mapbasic commands are sent to create
the table and enter the data row by row.
After about 4000 rows MI would hang and have to be terminated by killing
the
process. If
that occurred when we tried running MI again either by automation or as an
application it would hang. As an application it would not produce any error
message. It would just sit there and consume 99% CPU time. Also
reinstalling
MapInfo would not fix it. Infact the only way to fix it was to reformat the
drive and reinstall everything.
    We have found a way around it, by saving and closing the table every
100
records and reopening the table and repeating this we can avoid this
problem, we are wondering what is causing the crash though and especially
why mapinfo would not run afterwards. Any info would be
welcome. We are using VB6 SP4, WinNT 4.0 and MapInfo 5.5

Regards and  thanks
    Joe Dineen
    [EMAIL PROTECTED]





_______________________________________________________________________
List hosting provided by Directions Magazine | www.directionsmag.com |
To unsubscribe, send e-mail to [EMAIL PROTECTED] and
put "unsubscribe MapInfo-L" in the message body.






_______________________________________________________________________
List hosting provided by Directions Magazine | www.directionsmag.com |
To unsubscribe, send e-mail to [EMAIL PROTECTED] and
put "unsubscribe MapInfo-L" in the message body.

Reply via email to