Benoit Perroud created MAPREDUCE-5736:
-----------------------------------------

             Summary: Jobtracker to hang when jobs with lot of tasks running
                 Key: MAPREDUCE-5736
                 URL: https://issues.apache.org/jira/browse/MAPREDUCE-5736
             Project: Hadoop Map/Reduce
          Issue Type: Bug
          Components: jobtracker
            Reporter: Benoit Perroud
            Priority: Minor


The jobtracker (in MRv1) is progressing slowly when a job with lot of tasks is 
running. The reason is that JT.getJobCounters is holding a global lock, and 
with a big job (like 50+K mappers for instance), it could take while to 
instanciate the ``Counters`` class. This global lock prevent all other 
activities to run normally, queuing them and degrading the normal activities of 
the JT.

I was wondering if job.getCounters(), which is synchronized on a finer 
granularity (i.e. per job and not global) couldn't be taken out of the 
synchronized block.

On a more general idea, I was wondering if the usage of the synchronized 
statement in the JT shouldn't be re-thought. Or maybe all this has already been 
addressed in YARN.




--