Gera Shegalov commented on MAPREDUCE-5817:
------------------------------------------
The scope is:
We should redefine {{JobImpl.checkReadyForCommit}} to return {{COMMITTING}}
when
{code}
if (numReduceTasks > 0) {
if (isucceededReduceTaskCount == numReduceTasks)
return COMMITTING;
} else if (completedTaskCount == tasks.size()) {
return COMMITTING;
}
{code}
To address unprecedented nature, we can introduce a new state for
TaskAttempImpl LOST_COMPLETE that only mappers can go into from SUCCEEDED on
lost node.
On successful Job commit, we should generate an event that will kill all
outstanding unfinished map task attempts. Move one map task attempt form LOST
to SUCCEEDED (e.g, with minimum id) if there is none yet.
> mappers get rescheduled on node transition even after all reducers are
> completed
> --------------------------------------------------------------------------------
>
> Key: MAPREDUCE-5817
> URL: https://issues.apache.org/jira/browse/MAPREDUCE-5817
> Project: Hadoop Map/Reduce
> Issue Type: Bug
> Components: applicationmaster
> Affects Versions: 2.3.0
> Reporter: Sangjin Lee
> Assignee: Sangjin Lee
> Attachments: mapreduce-5817.patch
>
>
> We're seeing a behavior where a job runs long after all reducers were already
> finished. We found that the job was rescheduling and running a number of
> mappers beyond the point of reducer completion. In one situation, the job ran
> for some 9 more hours after all reducers completed!
> This happens because whenever a node transition (to an unusable state) comes
> into the app master, it just reschedules all mappers that already ran on the
> node in all cases.
> Therefore, if any node transition has a potential to extend the job period.
> Once this window opens, another node transition can prolong it, and this can
> happen indefinitely in theory.
> If there is some instability in the pool (unhealthy, etc.) for a duration,
> then any big job is severely vulnerable to this problem.
> If all reducers have been completed, JobImpl.actOnUnusableNode() should not
> reschedule mapper tasks. If all reducers are completed, the mapper outputs
> are no longer needed, and there is no need to reschedule mapper tasks as they
> would not be consumed anyway.
--