Dear Prof Zimmerman

By Islanding I mean its classic defenition which is disconnecting a part of
the network from the main grid while the embeded generator would be able to
supply stable operation of its network zone.
To elaborate on the question I could ask is there any parameter designated
in MATPOWER to turn the circuit breakers on and off or the only way is to
 redesign the studied network to implement the change?

Regards

On Thu, Feb 16, 2012 at 1:28 PM, Ray Zimmerman <[email protected]> wrote:

> What exactly do you mean by "islanding studies"? MATPOWER can solve cases
> with multiple islands so long as each island has a reference bus. I have
> recently written some code to find the islands by traversing the topology
> that will be included in a future version.
>
> --
> Ray Zimmerman
> Senior Research Associate
> 419A Warren Hall, Cornell University, Ithaca, NY 14853
> phone: (607) 255-9645
>
>
>
>
> On Feb 16, 2012, at 5:28 AM, iman wrote:
>
> Dear all,
>
> Does anyone know if it is feasible to do islanding studies in MATPOWER.On
> the other hand can you cut off the slackbus conenction?
>
> --
> Best regards
> Iman
>
>
>


-- 
Best regards
Iman