In the direct load control we provide incentives for the curtailed
load.here we set a virtual generator in order to include the incentives in
the objective function.But the virtual generator cost is (marginal
benefit-incentives).
for example i take the marginal benefit=38,incentive=20,the curtailed
load is 13.5MW.then the virtual generator cost is 18.now the objective
function includes
13.5*18 but not 13.5*20 which is my incentive.
how my incentive will include.
- direct load control Mounika Vanjarapu