thank you for your information بتاريخ ٢٠١٧/١٠/٢٥ ٦:٠٦ م، كتب "NAIDJI Ilyes" <[email protected]>:
> Hello, > in this case I suggest you to use most (Matpower Optimal Scheduling Tool). > You can see most user's manual. > > Regards. > > Ilyes. > > 2017-10-25 15:02 GMT+01:00 Mohammed Alhajri <[email protected]>: > >> But in this case, how i can add the constrains, like start up, shout >> down...? >> >> بتاريخ ٢٠١٧/١٠/٢٥ ٥:١٨ م، كتب "Mirish Thakur" <[email protected]>: >> >>> Hello Mohammed, >>> >>> If you want to run OPF for 24 hours then you need to have 24 cases (if >>> topology of grid changes). Set a for loop for 24 hours in such a way that >>> in each hour an individual MPC case will be build and OPF will be performed >>> for each hour. >>> This is a simple way I could suggest you according to your question. >>> >>> Regards >>> Mirish >>> >> >