thank you for your information

بتاريخ ٢٠١٧/١٠/٢٥ ٦:٠٦ م، كتب "NAIDJI Ilyes" <[email protected]>:

> Hello,
> in this case I suggest you to use most (Matpower Optimal Scheduling Tool).
> You can see most user's manual.
>
> Regards.
>
> Ilyes.
>
> 2017-10-25 15:02 GMT+01:00 Mohammed Alhajri <[email protected]>:
>
>> But in this case, how i can add the constrains, like start up, shout
>> down...?
>>
>> بتاريخ ٢٠١٧/١٠/٢٥ ٥:١٨ م، كتب "Mirish Thakur" <[email protected]>:
>>
>>> Hello Mohammed,
>>>
>>> If you want  to run OPF for 24 hours then you need to have 24 cases (if
>>> topology of grid changes). Set a for loop for 24 hours in such a way that
>>> in each hour an individual MPC case will be build and OPF will be performed
>>> for each hour.
>>> This is a simple way I could suggest you according to your question.
>>>
>>> Regards
>>> Mirish
>>>
>>
>