I’m afraid you’ll have to be more specific with your question. I assume you are 
starting with one of the tutorial examples in most_ex7_suc.m … which one? And 
what are the modifications you have made to adapt it for a 30-bus case, and 
where are you running into trouble?

   Ray


On Jun 30, 2020, at 2:02 PM, sebaa haddi 
<[email protected]<mailto:[email protected]>> wrote:

dear Matpower team

I hope some details about extending the three bus test system SCUC case study 
to 30 bus case system including for example one wind power or PV system at bus  
number 29, I try to read the MOST manual and understood the given example of 
three bus power system, and then visualizing all the associated patterns for 
SCUC problem, different  scenarios, but the problem when I try to apply on 
IEEE30 bus system including intermittent source I can’t write the files of 
transfer Matrix, ex_storage.m, ex_transmat.m, ex_wind_profile.m, ex_xgd.m, 
ex_xgd_ramp.m, idx_gen.m as well as other needed  files for IEEE30 , I’m 
preparing for a paper in this context

All my thanks