MATPOWER does not currently implement a multi-period AC OPF, but if DC OPF is
adequate, this is handled by MOST. See Example 5 in Section 7.2.1 in the MOST
User’s Manual<https://matpower.org/docs/MOST-manual-1.1.pdf> and
t/most_ex5_mpopf.m<https://github.com/MATPOWER/most/blob/master/lib/t/most_ex5_mpopf.m>.
Ray
On Oct 24, 2021, at 10:07 PM, 2254878263 <[email protected]<mailto:[email protected]>>
wrote:
Hi all
Does Matpower have any method to calculate the optimal power flow within 24
hours, with a period of 1 hour, considering the influence of generator slope
climbing and landslide.
Thank you very much.