On Mon, 8 Dec 2008, Rahul Nabar wrote:
I have a couple of jobs every week that show up with negative job remaining times (snippet below from showq).
Most likely these are jobs that should have finished but didn't; there are several situations in which they can appear, the 2 most common in my setup are: - one or more of the nodes from that job has died and the queueing system cannot terminate the job - a job not started via the TM interface (f.e. one using rsh to connect to remote nodes) for which the queueing system is not able to clean up
-- Bogdan Costescu IWR, University of Heidelberg, INF 368, D-69120 Heidelberg, Germany Phone: +49 6221 54 8240, Fax: +49 6221 54 8850 E-mail: [EMAIL PROTECTED] _______________________________________________ mauiusers mailing list [email protected] http://www.supercluster.org/mailman/listinfo/mauiusers