http://spaceflightnow.com/shuttle/sts115/060815frrbegins/

Shuttle readiness review begins; update on bolts 
BY WILLIAM HARWOOD STORY WRITTEN FOR CBS NEWS "SPACE PLACE" & USED WITH
PERMISSION
Posted: August 15, 2006

http://spaceflightnow.com/shuttle/sts115/060815frrbegins/

NASA managers kicked off a two-day engineering review today to assess the
shuttle Atlantis' readiness to blast off Aug. 27 on a long-awaited flight
to restart space station assembly.

Along with discussing the shuttle's external tank and the ongoing threat of
falling foam insulation, engineers and managers also will discuss what to
do about bolts holding the shuttle's KU-band antenna in place on the
forward right wall of the ship's payload bay.

A recent engineering review indicates two of the four bolts holding the KU
antenna support box in place are too short. Engineers cannot directly
inspect the bolts at the launch pad, but a paperwork review shows the bolts
in question may be engaged by less than 2.4 threads. The requirement is 8.4
threads engaged.

While the bolts were properly torqued, and while Atlantis has flown 26
flights in the current configuration, engineers cannot prove the bolts have
not, or will not, back out at some point, allowing the antenna box to break
free. Should it break loose during launch, it could fall the length of the
shuttle's six-story cargo bay and cause catastrophic damage.

Gaining access to the KU antenna at the launch pad is extremely difficult,
but sources say the engineering community wants to replace the bolts rather
than launch Atlantis as is. Kennedy Space Center engineers have developed a
plan to make the unprecedented repairs, but it's not yet clear what impact
such work might have on Atlantis' launch processing schedule.

Assuming managers at the flight readiness review approve the current launch
target, Atlantis countdown would begin Aug. 24 for a liftoff at 4:30 p.m.
on Aug. 27. The launch window closes Sept. 7. The current plan permits up
to seven launch attempts within that window.

The KU bolt fix, if approved, would require engineers to extend an access
platform into the open cargo bay from the payload change out room at pad
39B. A second platform then would be erected on the first to reach the
antenna box. Safety nets would be required because the work would take
place at a height of nearly 60 feet above the shuttle's aft bulkhead. In
addition, the shuttle's robot arm and a 50-foot-long boom used to inspect
the ship's heat shield would have to be moved to provide access.

A technician, resting on his side in very close quarters beside Atlantis'
external airlock, would then remove and replace the two bolts in question.
A major concern with working in such tight quarters is inadvertent damage
to nearby equipment, but engineers believe they can safely do the work.

A variety of other technical issues will be discussed at the flight
readiness review, including the status of Atlantis external fuel tank.

Atlantis will fly with an external tank that is virtually identical to the
one used to launch the shuttle Discovery last month. During the FRR before
that flight, NASA's top safety manager and chief engineer voted against
launching because so-called ice-frost ramps on the external tank, made up
of hand-crafted foam insulation, were formally classified as
"probable/catastrophic."

That classification means that over the original 100-flight life of a space
shuttle, there is a 50-50 chance that a piece of foam large enough to cause
catastrophic damage would break away from an ice-frost ramp and hit the
spacecraft.

The ice-frost ramps received that classification because they are made up
of foam that is manually applied on top of other foam. Recent engineering
studies show such foam-on-foam buildups can experience cracks because of
temperature extremes and pressure changes during fueling cycles. Such
cracks, in turn, can lead to foam shedding.

Under NASA's existing FRR procedures, the "probable/catastrophic"
classification left safety director Bryan O'Connor and chief engineer Chris
Scolese with no choice but to vote "no-go" at the end of Discovery's
readiness review.

NASA Administrator Mike Griffin ultimately approved Discovery's launch over
their formal objections, saying he didn't believe the probable/catastrophic
classification was justified and that the benefits of keeping the shuttle
on the ground until the ramps were redesigned were outweighed by the
programmatic need to restart station assembly.

NASA currently is in the process of redesigning the ice-frost ramps, but no
major changes have been implemented since Discovery's flight and it is
assumed O'Connor and Scolese will vote the same way they did last June.

During an interview shortly before Discovery took off July 4, Griffin
explained his earlier decision in detail.

"In order to get this to be a hazard, we have to assume that this flight is
going to release the maximum amount of mass we've ever seen," he told CBS
News. "Probably that's not going to happen, right? But that's what we
assume. Then we have to assume the mass comes off in chunks that are bigger
than we've ever seen. The biggest chunk we've ever seen come off with this
mechanism is .084 pounds. So we set the limit on this thing at .25 pounds,
which is the biggest chunk of mass that you could get off of an ice-frost
ramp because that's what the whole thing weighs. We've never actually seen
that, but we assume that could happen.

"Then we have to assume that all the mass comes off and it comes off in big
chunks and it comes off at the worst possible time, which is about a seven
or eight or 10 second window in there ... And then we have to say it hits
the worst place on the orbiter. So if all that happens, then we have a
hazard that we think rises to a level of real concern.

"Now, we're not ignoring it, we're going to redesign the ice-frost ramps
and we're going to fix it. But I ask myself as an engineer, what are the
odds that all those four bad things are going to come true over the next
two or three flights while we do a redesign? And I say to myself, not very
high.
And in fact, when we go and analytically study that, the odds come down to
like 1-in-400 or 500, which is well less than many other risks we're taking
on the orbiter."

Griffin agreed with the observation that complex systems fail in complex
ways and worst-case aviation failures do, in fact, occur. But he said the
risk posed by the ice-frost ramps is less, in his view, than the overall
risk of flying the shuttle at all.

"Rotating machinery would be well ahead on my list," he said, referring to
the shuttle's main engines. "Our micrometeorite and orbital debris hazard
is 1-in-200. I remember flight readiness reviews from my youth where every
moment was soaked up in turbopump seals. There are other hazards on this
machine that we accept in order to fly it.

"Now that's not good, either, and we're trying to transition to a new
system ... which will be at least 10 times safer than the shuttle on its
best day.
We can do better and we will do better. ... But if I can get individual
risks like foam debris down to one in many hundreds, then that's very
acceptable in comparison to the other risks which we accept to fly this
machine at all. And that's where I think we are.

"Everyone says why'd you overrule your chief engineer and your safety guy?
Well, that's why. Because I believe when we analyze this thing in terms of
what is likely to happen as opposed to a worst on worst on worst, the risk
is very acceptable."

Meanwhile, NASA flight planners have updated the timeline for shuttle
mission STS-115, moving space station undocking up one day and deferring
late inspection of Atlantis' nose cap and wing leading edges until the day
after separation.


--------------------------------------------------------------------
mail2web - Check your email from the web at
http://mail2web.com/ .



_______________________________________________
Medianews mailing list
[email protected]
http://twiar.org/mailman/listinfo/medianews_twiar.org

Reply via email to