Hi community,

 

-- First of all, apologizes in advance for the length of this email.  :-) -- 

 

As you know, we are participating actively on deploying Mifos at the MFI ENDA. 
During the last period, we have been working adding new features into Mifos to 
support ENDA's requirements.

 

[Here, some Background for the rest of community]

Increased Support for Mifos project built by OXIA:

 

* Ability to add group membership to individual clients - Complete

* Ability to remove group membership - Complete

* Ability to define Limiting product combination

* Ability to adjust multiple loan repayments - Complete

* Ability to disburse loans on non-meeting days - Complete

* Ability to schedule repayments on non-meeting days - Complete

* Electronic publishing - Complete

* Receipt and voucher printing from account pages - Complete

* Loan schedule independent of meeting schedule - Complete

* Group loan with individual monitoring - Complete

* Cash management/accounting interface - Complete

* Reporting Module (In-Progress: Remaining reports to be developed: four 
reports).

* Localizing Mifos into French (In-Progress)

 

 

On this level of the project, feature added were almost finished. Thus, we have 
planned to start working next week on ENDA data migration from its current 
system into Mifos.

(We will also be working on the wiki side to specify "how to we are preceding": 
detailed work-plan).

 

Since the information would be helpful for the entire community. I thought it 
best to share how we can proceed to Data Migration on the mailing list.

 

As a first step for this part of ENDA-Mifos Data Migration project, we had 
begun by:

1. Global analysis between the main entities of Mifos data model and ENDA's 
current system data model.

2. A detailed analysis of the data to import, related to the customer 
entity(either client or group). 

For each step we have specified the different columns to fill with the imported 
data and their respective tables. For several data imports, a conversion 
function has been specified too.

 

The next stage will cover those steps:

 

* 1. Data extraction from ENDA actual system

* 2. Data mapping analysis (between the old system and Mifos)

* 3. Analysis of the quality of data to correct or to complete

* 4. Development of tools of manual cleaning of data

* 5. Development of tools of automatic cleaning of data

* 6. Automatic data cleaning

* 7. Manual data cleaning 

* 8. Data cleaning validation

* 9. Data transformation and transfer preparation using Kettle 2.5.0

* 10.Data transformation and transfer execution

* 11.Data migration validation

* 12.Iteration of the steps 2 to 11 until transfer is validated (20% of total 
effort)

* 13.Data migration phase ended

 

The recommend approach provided by Emily (and which will be used) was to: Once 
our analysis is complete and we are ready to start building and testing the 
migration scripts, we should pick a version (ideally the most recent version) 
of Mifos against which to build our migration scripts.  And going forward, as 
we test our scripts, instead of migrating data into newer versions of Mifos 
(which might have db changes)-- we should always migrate into the original 
version we targeted.  Finally, we can then use the upgrade scripts to upgrade 
the data into the current version.

 

Thus, we will need to wait until the configuration work is completed before 
picking a version to build scripts against (that should wrap up in the next 2 
weeks or so).  That way, we can configure Mifos and then start migrating.

 

Finally, we will publish every day the progress report of the Data Migration's 
project.

Please comment if you need more detail or need further details.

 

With Regards,

 

_______________________________________________

M. Nazir LAJDEL

Technical Project Manager

OXIA

OXIA is ISO 9001 V2000 certified company - AFAQ QUAL/2005/25140

11, Rue Claude Bernard

1002 Tunis Belvédère

Tunisia

Tel.: +216 71 28 27 00

Mob: +216 23 43 43 06

Fax: +216 71 28 27 05

[EMAIL PROTECTED] 

Skype: nazirlajdel

www.oxiasoft.com

 

 

-------------------------------------------------------------------------
This SF.net email is sponsored by: Microsoft
Defy all challenges. Microsoft(R) Visual Studio 2008.
http://clk.atdmt.com/MRT/go/vse0120000070mrt/direct/01/
_______________________________________________
Mifos-functional mailing list
Mifos-functional@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/mifos-functional

Reply via email to