Hi,
 
I have one scheduling question to ask for help in constraint programming with Oz. If resource is discrete, how do I do with Oz scheduling tool. With Oz manual, Oz can solve scheduling problem with unary resource. But it doesn't express how to solve scheduling with discrete resource.
For the bridge building example, if there are one resource including two excavators, any one can do one same task. In other words, one task can be completed with one excavator in the resource. NO idea how to constrain the relation.
Thanks in advance.