On Friday 02 September 2016 10:33:41 Graeme Geldenhuys wrote:
> Hi Martin,
>
> How hard would it be to allow MSErun to do 2-4 compilations in parallel?
> The multi-thread/process number could be user configurable.
>
> For example, I have an 8 core system, and MSErun is compiling 30+
> independent projects all in sequence. If it could compile say 4 projects
> in parallel, the total time taken will be MUCH less.
>
> You can obviously default to 1 process at a time - so existing MSErun
> users will not be affected at all.
>
Added to wishlist. Not easy if done right. ;-)
It could be a good testcase for the MSEgui process component.