With the ability to just use start date with no due date, I have set
up a number of these in my outline. This has been working fine on the
Windows version. However, on the PPC, it seems that if the start date
only is selected, and a sub task is ticked "inherit parent places",
then the sub task shows on the to do even if the start date is in the
future.

Not sure if this is a bug or a setting that I have missed.

Regards

Stephen J
--~--~---------~--~----~------------~-------~--~----~