Hello there, I will try the conditional workaround you propose and let you know how it works for me. With regards to the dependencies, I also tried to keep a template directory but my projects have over 30 dependencies within them and I need to activate them pretty quickly and start using them right away. Fixing the dependencies is just not an option.
Thanks again. Gaston On Nov 30, 5:11 am, nschm873 <[email protected]> wrote: > > One of the worst setbacks I've found is the fact > > that dependencies cannot be exported in MLO or set up to be relative > > to a task. > > I do this differently with partially better results. I create a top > level directory called "templates" in my existing outline that I have > marked "hide branch in the TODO list." Now when I copy a project from > the templates hidden tree to an active tree the dependencies are all > there. They just point to the task in the templates project not the > active projects. This means you still have to go into the newly > created project and "fix" the dependencies. However, this is much > easier then creating them from scratch. > > MLO has an icon on the right side of the icons column that show > dependencies. You just need to go to those tasks that have that icon > and point the dependency to the newly created task. The name you need > to use is there already so it is simply adding the new dependency with > the same task name in the active project branch and then deleting the > old dependency of the same name. > > >For example, a task that can be answered Yes or No and that would > >trigger a different set of tasks to be activated or deactivated. > > As for the conditional tasks, I don't see why you can't manually do > that. If you create a "conditional task" you can have two trees under > that branch. If you are using a copy of the original project then you > can just delete the branch "this time" that you don't want to use. > > If you are using a recurrent project then you can simply mark the > other branch using "complete task and all subtasks". That ability is > located by right clicking on the task and going into the advanced > feature. There really aren't any repercussions that I can think of to > mark a subtree of a project completed since MLO only logs the project > being completed. > > Also you can highlight your "conditional" tasks with an automatically > created icon. In the automatic formatting rules add a rule that > displays a question mark based on something in the caption such as the > word "condition". Then you will get a question mark in the icons > column for any task with the word condition in it. Now it is pretty > easy to see which tasks are your "conditional tasks" and you can then > manually "trim out" the subtrees that you don't want to use. > > So basically one pass of your newly "recreated" project to fix the > dependencies and another pass to fix your conditional "choices" and > you are good to go. > > On Nov 24, 3:05 pm, Gaston <[email protected]> wrote: > > > > > Thanks Lisa, > > > I actually thought of that. but it's just too much trouble. I've > > noticed that there are a chunk of processes that stick together and > > need to be done in succession. The ability to branch would be really > > useful. > > > Also, because of the nature of the projects, dependencies are > > extremely important. One of the worst setbacks I've found is the fact > > that dependencies cannot be exported in MLO or set up to be relative > > to a task. Which means that I cannot create a "master task list" full > > of dependencies and re-use it without having to set up the > > dependencies all over again. > > > I absolutely love the way MLO handles the tasks in the To Do list. I > > would love to have that tool to guide me through my daily tasks at > > work, but I sincerely don't have the time to plan projects from the > > ground up every time around. > > > Rgds, > > > Gaston > > > On Nov 23, 5:12 pm, Lisa Stroyan <[email protected]> wrote: > > > > >For example, a task that can be answered Yes or No and that would > > > >trigger a different set of tasks to be activated or deactivated. > > > > It would be a bit kludgy but you could have two tasks, the "Yes" task > > > and the "No" task (which I believe could be hidden from the Todo > > > view), and then a different set of children tasks that are dependent > > > on each of those, so they only show up if Yes or No is completed > > > (checked). > > > > Of course later you would want to delete all of the other branch, > > > which would be a pain. > > > > Lisa > > > > ---------- > > > Lisa Stroyan, mailto:[email protected] -- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To post to this group, send email to [email protected]. To unsubscribe from this group, send email to [email protected]. For more options, visit this group at http://groups.google.com/group/mylifeorganized?hl=en.